Hi,
I am using CTM for production planning and creating PP/Ds orders.
But once I CIF the planned Orders to ECC and convert it to Production Orders, the start date for the production order in APO is same as the End Date. In ECC though the Production Order Start date is same as that of the Planned Order
eg: Planned Order (APO) start Date: 30-04-2010 & end date 05-05-2010
Production Order (ECC) start Date: 30-04-2010 & end date 05-05-2010
Production Order (APO) start Date: 05-05-2010 & end date 05-05-2010
Also once I convert the Planned Order to Prodution Order in ECC and take a CTM run the Production Order is not consuming the resource capacity.
Can anyone please respond how I can resolve this issue.
Thanks & Regards,
Sanjog Mishrikotkar