Hi,
We have a scenario where in user has done service entrysheet for excess value than PO.There is a SAP standard validation exist in the system for Quantity but not on value.
In our case,
First user has created a service Po with one serciace line for qty as 4 and gross price as Rs. 100 each , for total amount 400.
user has done service entry sheet for the same values. After creating service entry sheet user has changed PO by swapping values of qty( changed to 100 from 4) and gross price( changed to 4 from 100). This way he could able to post service entry sheet for more amount(760) than the Po total amount (400).
We want to restrict users from creating service entry sheet more value than PO. Please suggest if anybody has done any kind of development to meet this requirement.