Skip to Content
0
Apr 19, 2010 at 04:20 AM

Process Chain not running

240 Views

I have a process chain defined.

The Start Process is linked to following:

1) Process Type u2013 Load Data (ORGUNIT_ATTR) InfoPackage

2) Process Type u2013 Load Data (ORGUNIT_TEXT) InfoPackage

I executed the Process Chain manually.

The Process Type u2013 Load Data (ORGUNIT_ATTR) InfoPackage, is finished with GREEN color.

However, the Process Type u2013 Load Data (ORGUNIT_TEXT) InfoPackage, is not running. When I right-click on this Process Type ->Display All Jobs, the job still in Schedule status.

Why is it not running?