How does import of 2nd transport after failed testing in ZMHF happen?

Nov 29, 2016 at 02:15 PM

41

avatar image
Former Member

Hi All,

I am new to Solman and trying to understand how TMS is working in Charm. Can you please help to clarify the case of failed testing and new transport in the same Urgent Change (ZMHF)?

If errors occurred during testing, the tester returns the change document to the developer, by choosingStart of the navigation path ActionNext navigation stepReset Status to In DevelopmentEnd of the navigation path, so that the urgent change can be corrected in a new transport request.

Once new transport is ready, developer will pass Urgent change to test again by choosing “Pass Urgent Change To Test”. And what does happen with an old transport (the 1st one that moved earlier before testing failed)? Does Action skip already imported transport? Or does it import it again?

10 |10000 characters needed characters left characters exceeded
* Please Login or Register to Answer, Follow or Comment.

1 Answer

Best Answer
avatar image
Former Member Nov 29, 2016 at 03:11 PM
0

Hi Olga,

Only new change moves in.

Regards,

Harish Karra

Show 3 Share
10 |10000 characters needed characters left characters exceeded
Former Member

Hi Harish,

so Action skips already imported transport. Does it happen the same way when we want to change the state of ZMHF from "Authorized to Prod" to "Imported to Prod" having a transport in our CD that is already in prod (let's say was imported there manually"? Does action SMHF_PRODUCTIVE skip it's import to prod( since it's already there) and just update the status of Urgent Document?

Many thanks for your help!

0
Former Member
Former Member

Yes Olga,

It moves only the TR which is linked to your Urgent change.

You can test this scenario in your QA system (Check the import history so that you can find out the sequence and timings).

Regards,

Harish Karra

0
Former Member
Former Member

Thank you!