Changing delivery date on STO

860 Views

Hello,

I have a strange problem. Our users update the delivery date on STO's shipping from plant A to B after the GI already has been done on plant A.

We are on 6.0 and are using route/shipment scheduling and a few months back have also switched on ATP checking rule A.

When the item delivery date is changed, all the dates on the delivery schedule tab are recalculated. As they are changing that "today", SAP figures we cant ship in the past so calculates a whole new delivery date ==> Showing in the field "GR end date".

THat GR end date is used as the ATP date in plant B (in CO09), since we have quite long leadtimes (A in EU, B in US) this suddenly means the material is available much later than the actual arrival of the goods.

How can we stop that schedule line (in the delivery schedule tab) from recalculating whenever that item delivery date is changed. It is ok before the material has been GI'd in plant A, but not after.

Hope you are able to follow above!

THanks a lot!