Jan 08, 2019 at 02:35 PM

Schedule agreement price update

146 Views Last edit Jan 08, 2019 at 02:35 PM 2 rev

Hi, i need to quarterly change the Harnesses price according to the copper escalation/de-scalation.

The schedule agreement contains around 200 harness (part number), i currently use ME32l (item condition, Gross price, New validity period then enter the new price) to modify each part number price & then repeat the same process for the next part number.

Is there a way to change multiple part at the same time? or to upload an excel sheet containing the new prices?

Thanks