hi experts,

client has a raw material which is handling unit managed. user created a inbound delivery against purchase order.

after packing of HU the inspection lot gets generated and than goods reciept is posted .

users query is if he cancels the inbound deliovery or delete it will the inspection lot be cancelled? is it a standard SAP behaviour

i have cancelled the document in migo , out bound delivery is created but i am not able to do posting of goods issue as i cannot

pack HU there as material is in grey mode there.

i also tried VL09 the stock vanished from mmbe but inspection lot remains intact .

kindly guide

regds

satish