Hi Experts,
I have maintained the cost element in network profile under the activity type. When I create external activity in project builder system populates the default cost element entered in network profile BUT when I maintain Material Group in activity detailed data, system removes cost element and issues a message "Enter cost element".
System does not accept any cost element in the field. Please guide if there is some setting that I have missed
Thanking in advance
Warm Regards