Hi Experts,
i got a problem while creating planning higherarchy (mc61). error -Info structure S896 lacks the necessary structure,Message no. MA004.
Characteristics:
MRP Controller
Plant
Planning plant
Material
Key figures Unit
Sales 01
Production 01
Stock level 01
Target stock level 01
Days' supply 00
Target days' supply 00
Available capacity 01
Capacity requirement 01
Capacity load 00
info structure is generated proplerly.
plz suggest me....
pankaj