Apr 16, 2010 at 04:11 AM

book hours on activities/projects that have status TECO.

338 Views

Dear PS gurus,

Can we book hours in CAT2, on activities that have status teco, actually here we are using ZHR_timesheet for booking actual hrs instead of using CAT2, but now our requirement is that in status TECO, the system should not allow the user to book hrs, the system must give error message while entering hrs against network activities.

What is to be done to achieve this fuctioanilty. CAT2 or ZHR_timesheet??? is it possible??

Regards,

Ansar