Dear all,

I am using KKS5 to check Variance Calculation:

- Select the material with big variance

- Click Cost Element: to see the detail variance for each cost element

All activity type (machine, labor, eletricity) has NEGATIVE total actual cost

Could you pls tell me why the actual cost of activity type is NEGATIVE?

How can I fix it?

Thank you very much!