Hi,

one of the WBS element having no costs but auc created through Investment measure. But while closing the WBS element

system throwing error as follows" Go to the asset in construction for the WBS element and correct the error that appears there".

now client wants WBS to be closed without deleting AUC. Please suggest us how can i close WBS without deleting

AUC attached to it. Please advice.

Regards

Sreenivas.P