Skip to Content
0
Former Member
Apr 15, 2010 at 04:50 AM

Production Order in MTO process!

135 Views

Hi all experts!

My client have requirement. Prodcution order of FERT will genarate by sale order. In BOM of FERT, they have many Semi-Finish good. But they dont want to genarate production order for semi-finished good(they do in footware industry so fert have many parts in BOM). And they don't run cost for Semi-Finish good also.

In semi-finishgood(parts), they want to do GR for tracing status of production order of Fert only.

How to cover their requirement?

- Use 1 production order only for hold BOM of Fert.

- Still do GR for Semi-finish goods(Now they do good receipt base on production order of Fert, not by themself).

- Not consider standard cost(not costing) for Semi-Finish Good (parts, because 1 Fert they have many small parts)

Please advise me solution.

Thanks all of you!

Tony