Apr 15, 2010 at 03:11 AM

MRP question

35 Views

I'm wondering why MRP doesn't create planned orders for requirements in the future? Is it because there is some setting that I need to maintain to make the system act differently?

For example, i have available stock of 10,000,000 and I have requirements:

4/10/2010 2,000,000-

5/10/2050 5,000,000-

6/10/2010 3,000,000-

7/10/2010 50,000,000-

8/10/2010 50,000,000-

9/10/2010 50,000,000-

When I run the MRP, system is not creating planned orders for 7/10/2010 - 9/10/2010. Why is it acting like this?