I want to run the demand management and MRP for my client

my senario is MTS and having prodution as per production version

I want to put my Plan in MD61 as per my diffrent production version for a same product

but when i put the plan in MD61 by maintening diffrent PV maintening at schedule lines tab it only select one prod. version

and if i put plan in MD61 without maintening PV then after MRP run system taking default PV

how can i map this in SAP

Regards

Sachin

Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

2 Answers

  • Best Answer
    Apr 14, 2010 at 05:42 AM

    Dear,

    You can put two line item in MD61 so accordingly you can assign the PV to schedule line tab.

    Or go for Quota Arraignment.

    Search on SDN you will get all details steps to do this.

    Add comment
    10|10000 characters needed characters exceeded

    • Hi

      In the MRP view 1 there is Lot size data you have to maintain the ES while while using the quota arrangement for the material.

      If there is no ES in OMI4 then you need to maintain the ES Lot-for-lot order quantity WITH SPLIT

      Check and revert

      Regards

      Anupam Sharma

  • avatar image
    Former Member
    Apr 14, 2010 at 05:45 AM

    Dear Sachin,

    in my understanding

    1) in same period you cannot assign demand to Two PV'S in MD61, even in schedule line tab

    2) you need to go with Quota arrangement in that case

    Regards

    Madhu