on 04-14-2010 6:39 AM
Dear All
I want to run the demand management and MRP for my client
my senario is MTS and having prodution as per production version
I want to put my Plan in MD61 as per my diffrent production version for a same product
but when i put the plan in MD61 by maintening diffrent PV maintening at schedule lines tab it only select one prod. version
and if i put plan in MD61 without maintening PV then after MRP run system taking default PV
how can i map this in SAP
Regards
Sachin
Dear,
You can put two line item in MD61 so accordingly you can assign the PV to schedule line tab.
Or go for Quota Arraignment.
Search on SDN you will get all details steps to do this.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Dear R
Thanks for ur reply
I already try this by putting two lines in MD61and assingn two diffrent PV with diffrent planning version (00 & 01) then it will create two diffrent Independent req. up to here its fine.
but when i run the MPR it will club the requeriment and create a single planned order with first production version i dont want to club the requirement i need system should create diffrent plannned order for diffrent PIR
Regards
Sachin
Dear,
Then go ahead with Quota arrangement it can split the requirements for different production versions
Steps,
Maintain the production versions in MRP4 view of the material master along with the lot size and validity dates.
Maintain the Quota Arrangement in MEQ1 and enter the Quota for the production versions along with their % of usage
Maintain splitting allowed for Quota for the Lot size in OMI4,this must be set for the lot size which is mentioned for the final
product in the material master for which quota is maintained.
.Maintain Quota arrangement usage 4 in the material master for the product for which quota is maintained.
Please refer this link,
http://help.sap.com/saphelp_47x200/helpdata/en/75/ee115f55c811d189900000e8322d00/frameset.htm
Regards,
R.Brahmankar
Dear R
I maintened all the setting given by u
Maintain the production versions in MRP4 view
Maintain the Quota Arrangement in MEQ1 and enter the Quota for the production versions along with their % of usage
Maintain splitting allowed for Quota for the Lot size in OMI4
Maintain Quota arrangement usage 4 in the material master for the product for which quota is maintained
But still after running MRP system is not spliiting my planned quantity as per my quota it only creating one planned order
Regards
Sachin
Dear Sachin,
in my understanding
1) in same period you cannot assign demand to Two PV'S in MD61, even in schedule line tab
2) you need to go with Quota arrangement in that case
Regards
Madhu
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
107 | |
12 | |
11 | |
6 | |
5 | |
4 | |
4 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.