Hi,
This is my scenario:
Material A is composed by material B. When the stock of material B is 0, MD04 does not take in account the time to provisioning Material B when a Material A has to be produced.
Example:
Time to create Material A: 3 days. Created using a Purchase Requisition (subcontracting).
Time to provisioning Material B: 6 days.
MD04 (for Material A) always shows 3 days (today3days), never mind if the quantity of material B in our warehouse is 0 (in this case should be: today6days3days, but always is today3). Maybe the problem is the rescheduling date at MD04 (always is today, not today+6days)?
What do I have to modify? (Maybe master material?)
Thanks in advance,
Ricard.