Identify method of locking & reporting PM02 work orders which are not completed, so they can not be closed and should not be counted in PM02 work order completion statistics.

Eg If there is a time duration of a month to complete the order and order is not completed within timelines then:-

1:- The Order should get closed so that nobody can make changes in it.

2:- We can check the completion rate of work orders in the month.

However I know how to lock a single order. But how can we make this happen so that after a month order get locked itself.

Many Thanks in Advance

Regards,

Vineet

Edited by: Vineet Guliani on Apr 13, 2010 10:10 AM

Add comment
10|10000 characters needed characters exceeded

  • Follow
  • Get RSS Feed

1 Answer

  • author's profile photo
    Former Member
    Apr 13, 2010 at 09:17 AM

    Hi Vineet,

    You need to create customized transaction for this function. Take help of your ABAP team and they need to create a program and a tcode which will have your requirments as input.

    This program will use functional module DFPS_ORDER_CLSD_SET and close your orders. Input of that tcode can be order number or order type and date. In out put this FM will close all orders.

    Add comment
    10|10000 characters needed characters exceeded

    • Former Member

      Hi Gurus,

      There is a confusion. If different work orders have diffrent end dates. Then how can we lock the orders having diffrent diffrent end dates.

      Regards,

      Sanjay

      Edited by: Sanjay 1t on Apr 14, 2010 8:18 AM