Good Morning,
I have been facing a problem with basic date. I give a example:
WBS A
Task 1
earliest start date: 1/1/2010
earliest finish date 6/1/2010
duration:6
WBS B
Task 2
earliest start date: 7/1/2010
earliest finish date 8/1/2010
duration: 2
Task 1 has FS relationship with Task 2.
I confirmed task 1 earlier than earliest finish date at 3/1/2010. When I schedule de project definition, the system doesn't update the dates related with task 2. The earliest date shoud be 4/1/2010 (start) and 5/1/2010 (finish date). What I have to do to fix this problem. When Task 1is late, the system update correctly basic dates of tak 2.