Hello everybody,
We will start working with repetitive manufacturing in SAP and I have a couple of doubts that maybe you can answer:
- When I launch the MRP, the planned orders are directly created without production version, is there any way to indicate a production version by default when the MRP creates the planned orders?
- In our model we have just one production version per material. I have notice that although the planned orders are created without production version, if during backflusing I indicate then production version, the quantities are automatically discounted from the planned orders without production version. If I create the planned orders without production version, which are the problems that I can found?
Thanks in advance,
Laura