hi! All
Ran MRP for a material through MD02 today with NETCH, 3,3,1,3 but while checking the Rescheduling Date with exception flag 30 iin MD04 the dates are in past and there is no Pldord for the current Date & some of the pldord are without Rescheduling Dates why is it so, what it indicates.
How to solve the problem.
Regards
Kv