Hi Experts,
Please tell me following:
In which table I will find link of dependent requirement & planned order.
I have run MRP for FG material ( MMR - 20000050) . I got planned order no 10001 for FG material. Then I saw MD04 for ROH material ( MMR - 10000029 ) . Where I saw dependent requirement & planned order for MRP element 20000050 & 25305.
When I double click on depenent requirement I got dependent requirement no 28620 & planned order no 10001 of FG material.
Now my requirement is in which table I will find link of dependent requirement no 28620 & planned order no 25305 of ROH material
In RESB we got link between dependent requirement no 28620 & planned order no 10001 of FG material only do not got link of dependent requirement no 28620 & planned order no 25305 of ROH material.
Please help.