Skip to Content
0
Former Member
Apr 11, 2010 at 08:05 PM

Scheduling Issue at subassembly level

55 Views

Hi Experts,

In REM scenario we are having two levels of BOM e.g. Finished Good X and subassembly Y both are produced in house with REM on different production lines. The total time taken to produce one finish good is 2hrs which includes 1 hour for producing Y and one hour for producing X, while running MRP with lead time scheduling system creates RSQ for the finished good X say on 13.04.2010 and at the same time subassembly RSQ is created on 12.04.2010.

Whereas practically system should create RSQ for Subassembly on the same day and the finish time of subassemblyu2019s RSQ should be equal to start time of finished goods RSQ.

Is there any specific setting required for this?

Regards

CS