PM PP Integration

Hi experts,

If I assign a PP work center in Main work center field of equipment, as soon as, I assign same equipment in order, the main work center is automatically copied in order work center and main work center fields. In this case if I continue with PP work center and run IW42 then all the cost of PP labor/work center would be debited on order.

a)Now, I am being used PP work center just for checking overload message on work order then I first dispatch the work order to next possible date (by using PP representative)/ confirm on the same date {by using capacity over load message on work order (Detain info and finite scheduling)} and finally I replace PP work center by PM work center inorder to get PM work center cost.

I want to know

Is this best practice?

what is the difference between Detail info and finite scheduling data of capacity overload message on a work order?

b) Consider If I use PP work center Pack0001 and I assign this to a work order, It is found overload on 12.042010, 8:30am to 12042010, 9:30am on a production order, then

How would I get automatic time scheduling start from 12.042010, 9:31am to 12042010, 10:31am on a maintenance activity (in operation tab of work order)? (If I use work as 1 hr)

After dispatching the above order, then I would replace PP work center by PM work center, so

what settings should be made to keep same time scheduling on an order as we did for PP work center?

Regards,

Add comment
10|10000 characters needed characters exceeded

  • Follow
  • Get RSS Feed

1 Answer

  • Best Answer
    avatar image
    Former Member
    Apr 12, 2010 at 01:59 AM

    A) Best Practice generally is industry specific,however in your case, i don't think none of them would suggest to assign a PP work center for a maintenance order for initial scheduling.In all cases the work center is would be the executing and or managing work center.

    The detail info option would list out the Availability of the work center, the requirements details and the associated overload on a period basis for each and every operation of the order

    Finite Scheduling would try to auto schedule the work according to the availability and load.

    Both these are dependent on the overall profile associated to Plant / Order type combo in OIOI for Release.

    Regards

    Narasimhan