on 04-10-2010 12:36 PM
Dear All,
when we create a Asset PR through WBS or Network it is not Updating in Commitment cost, against PR i created PO and then did GRN, but it is not Updating in Actual cost also for the given WBS
So how to create Asset through WBS kindly suggest
Thank you,
Regards,
Naveendra
Please read this note 61414, it may help you
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi
For commitment ans Actual Cost Updation please check you cutomization settings.
AUC (Asset Under Construction) gets created once WBSE Element is Released provided that Investment Profile is defined in Project Profile configuration.
Asset number get created after Full settlement of WBSE and Asset Completed.
Please check.
Swapnil Kharul
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.