Hi Experts,
When we were doing T.Code: CK11N ( cost estimate with Quantity structures) the following error msg is displayed.
"Error Msg: Costing Item #0001 is not assigned to cost component"
could you tell me how I can move forward.... Thanks in Advance for your valuable solution...
Regards,
YK
Hi,
costing item #0001 uses a cost element that is not assigned to your cost component structure.
The cost component structure assigned to the costing variant can be seen in T-code OKKN, double-click the costing variant, chek "assignments" click "cost-component structure".
The cost component structure definition is done using T-code OKTZ.
Best regards, Christian
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
103 | |
12 | |
11 | |
6 | |
5 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.