Process order

Hi Experts,

I have created master recipe with status as 1 created & BOM with status 2 Inactive for FG material in plant 1050.

I created process order for same FG material in same plant. Then system show me message that Master recipe not released & NO valid BOM exist.But allow me to release & save order. How it is possible if recipe is not release even system allow to create order. As per me,system should not allow to release or save order. This happen in quality server & devolement server.

But when I try in production server for same scenario system does not allow me to create order.

Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

3 Answers

  • avatar image
    Former Member
    Apr 09, 2010 at 06:14 AM

    Hi

    If the BOM status is inactive- still we can create Production Order, system will pop up warning message if you click no . it will proceed further. But if you check BOM component screen there will not be any components.

    So no GI.

    it will be the same in all servers.

    Please check

    regards,

    Srihari.M

    Add comment
    10|10000 characters needed characters exceeded

    • Former Member

      Hi,

      I have clearly wrote in my thread that if recipe is in create status 7 BOM is in A Inactive status, system does not allow me to create order in Prod server but allow me in dev & Quality server. How it is possible.

  • avatar image
    Former Member
    Apr 09, 2010 at 06:22 AM

    Hi Raja,

    Please try status 4 - Released General in the master recipe and in the BOM, use status 1 - Active.

    Hope it helps.

    Regards,

    Kaushik.

    Add comment
    10|10000 characters needed characters exceeded

  • Apr 09, 2010 at 06:23 AM

    Dear,

    Please check the setting of COR4 for Component verification and requires approval for your order type and plant in production and development server.

    If you now create a process order with this recipe, the system generates information message 40102 (CO261 ).

    This is standard for process orders, because in such cases you must work with recipes requiring an approval.

    Regards,

    R.Brahmankar

    Add comment
    10|10000 characters needed characters exceeded

    • Dear,

      Please refer the OSS Note 416344 - Consulting: Creating a process order, recipe status

      All detail information given for the message 40102 and CO261 also the settings for the message type in Transaction O04C.

      Regards,

      R.Brahmankar