Hi Friends,

I am trying a very simple scenario, where there is a WF; Details are below

Step 1 - A activity step with latest end deadline monitoring; Dead line has been modeled and I have added a process control step in the modeled branch where I have mentioned in Controltab->Function "Cancel work item" and WF step equal to step 2( a step after step 1).;

Step 2 - step 2 is a dialog step too.

But at run time when deadline is reaching process control is not logically deleting the step 1 & also not switching control to step 2 ..

In log it is showing Orphan step after step one and in Graphical log control is showing at Step 1 only.

Regards