Hi all,

How can I activate sch. parameters like shift factor,factory calendar in multiple counter plan?I have activated "special function in maintenance plan' in customization.Thanks in advance.

rgds

rajib

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

By activating special function setting you can use enhanced multiple counter plan.

All other relevant scheduling parameters remains active irrespective of the setting you have made. I think shift factor,factory calendar are not relevant for multiple counter hence remains inactive.

So you can proceed with using enhanced multiple counter plan functionality.

thks

Edited by: Talankis on Apr 8, 2010 4:28 PM

Former Member
0 Kudos

HI

Thanks for your quick response.How can I populate scheduling parameters shift factor,factory calendar etc. in multiple counter plan-IP43 like single cycle plan-IP41.

rgds

rajib

former_member546319
Contributor
0 Kudos

Hi Rajib,

As stated above, the parameters like shift Factor, Factory Calender etc are irrelevent for Multiple Counter plan. Hence they will not appear in IP43. What is your actual requirement?