Dear All,

When I create scheduling agreement and at the time of saving system give me the document is incomplete message with following area,

Shipping Point/Receivi

Loading Date

Material Avail. Date

Transptn Plang Date

Goods Issue Date

My material is not stockable no, system will not run any availability.

Plus I remove the availability check from scheduling agreement, but when I put the order quantity system by default no update the confirm quantity, i will do it manually.

Regadrs,

Accepted Solutions (0)

Answers (2)

Answers (2)

former_member301027
Participant
0 Kudos

Issue Resolved, Have some material type issue.

Thanks and Regards

sidi_reghioui
Active Contributor
0 Kudos

What type of scheduling agreement are you using?