Sceduling Agreement (Incomplete)

Dear All,

When I create scheduling agreement and at the time of saving system give me the document is incomplete message with following area,

Shipping Point/Receivi

Loading Date

Material Avail. Date

Transptn Plang Date

Goods Issue Date

My material is not stockable no, system will not run any availability.

Plus I remove the availability check from scheduling agreement, but when I put the order quantity system by default no update the confirm quantity, i will do it manually.

Regadrs,

Add comment
10|10000 characters needed characters exceeded

  • Follow
  • Get RSS Feed

2 Answers

  • Apr 08, 2010 at 12:49 PM

    What type of scheduling agreement are you using?

    Add comment
    10|10000 characters needed characters exceeded

  • Apr 15, 2010 at 01:23 PM

    Issue Resolved, Have some material type issue.