Hi,

We are doing settlement of project costs to AUC when we encountered Message No. BP603 for some of the items. How could we correct this error? We did not encounter this error for our past settlements. We also did not make any change in the configuration settings.

Accepted Solutions (0)

Answers (2)

Answers (2)

Former Member
0 Kudos

Hi,

Please check Note 159850 - Settlement within a project.

Similar question was raised before: fyi.

Regards,

Tom

Rachel_Tang
Advisor
Advisor
0 Kudos

Please check what is your budget value in CJ31 if the Budget in CJ31 is already consumed then you may need to check why the budget is consumed or checked during your postings.

Note "159850 Settlement within a project" has explained the behavior, you may check it in detail.

Former Member
0 Kudos

Hi Rachel,

We have checked the budget but it still have sufficient balance to cover the settlement costs.

former_member203108
Active Contributor
0 Kudos

try running CJEN and CJBN...then run settlement and see..

Former Member
0 Kudos

Hi Ahmed Rifaee,

We ran CJBN and tried to settle. However, we encountered the same error.

Thank you.