Skip to Content

RABEST_ALV01 - work list

Hi SDN,

How can I select fiscal períod (13) from new work list (button WL) (workflow task - Retirement without revenue) on RABEST_ALV01.

In the screen Retirement without revenue we can edit posting date, but not the fiscal period (this field is missing!)

Thanks.

Regards,

Maria João Rocha

Add comment
10|10000 characters needed characters exceeded

  • Follow
  • Get RSS Feed

1 Answer

  • Apr 07, 2010 at 05:13 PM

    according to sap note 199815 - mass retirement is the special períod it is not possible.

    "You cannot enter any periods in the mass retirement with or without sales

    revenue. As a result, you cannot make postings in a special period, that is

    the period is determined from the posting date."

    Best Regards,

    Maria João Rocha

    Add comment
    10|10000 characters needed characters exceeded