I have the following scenario

BOM Header: Material A (MTO)

Component: Material B (MTO)

Material A is produced in-house with one operation subcontracted.

Operation 1: In-house

Operation 2: Subcontracted

Operation 3: In-house

When the Sales order is created for Material A, MTO demand generated for both Material A & Material B.

After the MRP run, convert Planned Order for Material A to production order. No a new purchase req. is generated for Material B which is non MTO. There are two purchase req for material B- one is MTO and the other is MTS. Any reasons why this is happening.