I have the following scenario
BOM Header: Material A (MTO)
Component: Material B (MTO)
Material A is produced in-house with one operation subcontracted.
Operation 1: In-house
Operation 2: Subcontracted
Operation 3: In-house
When the Sales order is created for Material A, MTO demand generated for both Material A & Material B.
After the MRP run, convert Planned Order for Material A to production order. No a new purchase req. is generated for Material B which is non MTO. There are two purchase req for material B- one is MTO and the other is MTS. Any reasons why this is happening.