Hi all;
I have a question for you.
I am have 3 mechanics at plant with different hourly rates for activity internal labor LABO.
We created a work center for each of this mechanic and assigned to a cost center 110010 with activity LABO and hourly rate.
Technician Rate Acitivity
T1 $10/Hr LABO
T2 $20/Hr LABO
T3 $30/Hr LABO
I wan to capture a cost of individual technician who has worked on PM order.
e.g. If technician T2 worked on a PM order 1 for 3 hours and T1 worked for 2 hours, I should be able to capture $60 + $20 = $80.
Can I capture this information after settlement of PM order??
How this can be done??