unable to chage the status of normal correction to confirm successful test

Hello,

I am unable to chage the status of normal correction to confirm successful test in solman. Its shows error:

Not all test transports are imported .

I have imported the test trasnport in to test system successfully but still i am getting this error . I have also checked blogs in SDN but non of them refers to any solutions. But I can see lot of people have faced this issue.

My configuration is fine and no error in application log.

Can any body help me to find the resolution for this problem? answers will be rewarded.

Regards,

Bhavesh

Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

3 Answers

  • avatar image
    Former Member
    Apr 06, 2010 at 09:33 PM

    Hello Bhavesh,

    Please review/implement the following SAP Note to see if it helps resolve your problem:

    1352886 - ChaRM: All ToCs checked while setting status

    As well, check this SDN Blog to see if it also helps you out:

    /people/dolores.correa/blog/2009/07/23/change-request-management-scenario-working-examples

    Thanks,

    Mark

    Add comment
    10|10000 characters needed characters exceeded

    • Former Member Former Member

      Hello,

      Can any body help me to resolve this issue , ? I am still not able to change the status of change document to "consolidate"

      Thanks,

      Bhavesh

  • avatar image
    Former Member
    Apr 07, 2010 at 12:24 PM

    Hello Christoph,

    Thanks for the update. but i think this will not be a good solution any ways i will try this is nothing else work .

    Regards,

    Bhavesh

    Add comment
    10|10000 characters needed characters exceeded

    • Former Member Former Member

      We had a problem in the past where the export / import job running on the satelite systems were giving problems.

      And we had a similar issue when trying to chage the status to "succesfully tested", where during the lifetime of the correction document multiple TOC's were created. But 1 or 2 TOC's were never created, but Charm checks that all TOC are imported.

      The solution to this, was to manually redo the export of the missing TOC's.

      And afterwards, we could go to successfully tested, and auth for import...

      It does mess around with the seq of the TOC's, but the release of the original does sort it out again.

  • avatar image
    Former Member
    May 03, 2010 at 10:13 AM

    Hello,

    I have resolved this problem. Please refer OSS ticket 41398300/ 28418300.

    Regards,

    Bhavesh

    Add comment
    10|10000 characters needed characters exceeded

    • Former Member

      Hi All,

      I have same problem. I can not move status from 'to be tested' to 'consolidated'.

      But, in my case, TOC is already imported. Original transport are already imported too (do manually via task list)

      Could you write down here the solution that mention above in OSS ticket 41398300/ 28418300.