Hi,

In the scenario of settlement projects, when I run the CJ88, the budget amount is decreasing of the PEP. This is happening because the settlement is set to occur on the same account in which expenditure was made. But I need the amount of appropriation does not reduce the budget. In this scenario I cant configure the account settlement (OPTK). Anybody knows if exist another method (user_exit, ...) to settlement, without consume budget?