Hi All,

I have a material maintained in 3 plants say A, B, C. The stock is also maintained in all 3 plants. The production happens only in plant C. MRP is run in plant C.

But while MRP run, I want that system should consider the stock in all plants - A, B, C.

Regards,

Manish

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

Hi Manish ,

In SAP R/3 you can run MRP in

1.single item single level

2 Single item multi level

3 Plant level

4 In background

so its not consider the stock from other Plant ,for crossplant planning APO is the option

also with Special procrument key in MRP3 view in material master . Production,withdrawl and stock transfer can be possible from alternate plant but not stock consideration while MRP run

Regards

Girish

Former Member
0 Kudos

Hi

It can be achieved only by APO.

In R/3, we can run MRP at Plant Level (Maximum). When you run MRP at Plant C, System will consider the stock at C Only.

From Plant C to Plant A requirements should flow (It can be done by using special Procurement Key)

From Plant A to Plant B Requirements can flow by using special procurement Key

Here we should understand that from Plant C requrements can flow to Plant A only directly.

Generally we will requirements that system should consider the stock in all plants as well as requirements should go to 1 or more plants automatically.

We can do this by using Quota arrangement. But it doest not solve the issue.

regards,

Nag

former_member700523
Participant
0 Kudos

Hello All,

Thanx for all replies. Closing the thread with points given to all replies.

Regards,

Manish

Answers (1)

Answers (1)

Former Member
0 Kudos

Dear Manish,

in my understanding it is not possible in SAP R/3

Regards