on 12-23-2018 5:40 AM
Hello Gurus,
Hope to get your professional introduction. The case is like below:
Item 2000 0000, its purchasing group in material master data is "100",
This item has a source list, contains vendors "1000", "2000" and "3000", each vendor is assigned to a purchasing group:
Vendor "1000" is assigned to purchasing group "100",
"2000" is assigned to group "200",
"3000" is assigned to group "300".
Then how can I make the purchase requisition be assigned to group "300" automatically when running MRP without changing the material master data?
Thank you and looking forward to your professional reply!
Hello DOC11,
Extra info. for this case:
Vendor "1000" is assigned to purchasing group "100", with info. record PB.
"2000" is assigned to group "200", with info. record PB.
"3000" is assigned to group "300". with info. record PL.
We hope that even in master data it's assigned to 100, because "3000" has a PL, so after MRP running, the plan order / PR will be assigned to "300".
Months later, if "2000" has a PL info. record, while "3000" PL is expired, it will be auto. assigned to "200".
Is it possible? Thank you!
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
108 | |
12 | |
11 | |
6 | |
6 | |
4 | |
4 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.