Hi,

In LSO_PSV2 - Right click on "E" - Participant List -

Cost Center is Empty.

How I can do to bring the data?

Thanks in advance, Sony

Accepted Solutions (0)

Answers (1)

Answers (1)

Prajwal
Advisor
Advisor
0 Kudos

Hi,

For that you need to first maintain Cost for the participants.

For that please follow the steps below.

1. Transaction LSO_PSV1.

2. Select the course, Menu Participation-> maintain fee list(CTrl+F9)

3. Select the attendee and press F9.

4. Maintain fee by selecting 'Activity Allocation'.

This will populate the cost center in the report.