Project stock options: valuated and non-valuated

Former Member
0 Kudos

Hi Experts

In some discussions, i have been told that the 'valuated project stock' option is adaptable for customer projects where as 'non-valuated project stock' option is for cost projects. is it right?

May explain what circumstances non-valuated project stock option is chosen?

If we choose non-valuated project stock option, the results analysis is must, is it right?

warm regards

ram

Accepted Solutions (0)

Answers (2)

Answers (2)

nitin_patoliya
Active Contributor
0 Kudos

Refer note 533207 for more information on Valuated and non-Valuated stock.

With Regards

Nitin P.

Former Member
0 Kudos

Even Customer projects may be Non-Valuated. It depends on client requirement.

Regarding result analysis it is not must in case of valuated. Again depends on customer requirement. Resulst anlysis can be used for both Valuated as well as Non-valuated projects.