on 01-02-2019 8:45 AM
In a rework scenario. I maintained all the data ie trigger point, reference operation etc. But while confirming production order rework tab is grayed out. I check control key, But there also i maintained the control key for rework. Please tell me the solution regarding this.
Dear Mr.Dhiraj Dua,
you can check in configuration " Single Screen Entry of Confirmations" (Tcode OPK0)
Best regards
Anita