When we are running MRP both schedule line and PR are getting generated. Please advice what might be the reason for this.
Thanks and Regards
Pavan
Hi
Check the source list (ME01). Probably your requirements (due date) are falling before the source list start date.
Regards
Eduardo Chagas
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
You can have either or both PR and scheduling line generated. If you just want PR generated and no scheduling lines, besides Scheduling lines in MD01, use option 1 - No schedule lines, and then run MRP, only PR will be generated no schedule lines
Edited by: Afshad Irani on Apr 5, 2010 9:37 AM
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi
Check the validity period of your schedule agreement.If requirement quantity falls outside the validity of the schedule agreement, PR will be created.
Regards
Sandeep
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
100 | |
12 | |
11 | |
6 | |
6 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.