Carryforward PR/PO Commitments document-wise

Dear Sir,

Is there any T.code or program through which we can carryforward PR and PO commitments seperately and also by PR/PO document wise. In the same way, we also need to carryforward the budget with the selection of WBS.

Regards

Mudit Gupta

Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

2 Answers

  • Apr 01, 2010 at 08:52 AM

    As I Know it's possbile at level of Project , Network for Commitment Carry Forward. And For Budget the same is at level of Project.

    CJCF - Carry Forward Commitment

    CJCO - Budget Carryforward

    Check above Tcodes. I belive It's not possbile for independent PR/ PO becaseu there is lots of dependancy between these Tcodes.And budget works at level of WBS only.

    With Regards

    Nitin P.

    Add comment
    10|10000 characters needed characters exceeded

  • avatar image
    Former Member
    Apr 01, 2010 at 09:17 AM

    Sir,

    This is true that these transactions works only for Project, Netowrk Commitments

    But we need to carry forward for WBS i.e. if there are 4 PR's and 6 PO's on one WBS, we may be able to carry only 2 Pr's and 4 PO's by putting the same WBS.

    Regards

    Mudit Gupta