Hi Experts

We are using SolMan 7.0 SP16 and tring to apply ChaRM functionaliy for ERP 6.0 enviornment.

Our ERP 6.0 client landscpe is as follows

DEV QAS PRD

-


100 100 100

200 200 200

300 300 300

400 400 400

500 500 500

  • Client control of transport route is activated

  • Transport request from 100 only goes to client 100 in QAS and client 100 in PRD

  • Transport request from 200 only goes to client 200 in QAS and client 200 in PRD

  • and so on

[Question]

  • Does SolMan ChaRM support the above transport management?

  • Is anybody acutally doing such a transport management with SolMan?