Thanks Asif,
But my sequence of creation was as under
PR (ME51N/CJ20N) > ME41 > ME31k > ME21N
In above, sequence, when PO is created in me21n with reference to Contract , PR No. field is blank.?
pl see below, the ekpo table, upto contract creation there is reference of RFQ as well as PR
but in case of PO creation , there is only reference of Contract , no FRQ, no PR reference is saved.
Hello Umesh,
The contract is not created with reference to the PR, but with reference to the RFQ, so the PR number displayed in RFQ's EKPO entry, not in contract's item.
So if now a PO is created with reference to the contract, the PR number will not be filled in PO automatically, but if a PO is created with reference to the RFQ, the PR number will be proposed.
Regards,
Diana
Hi Umesh,
Since you have created a contract already, the purchase requisition is closed.
For tracking the purchase order, purchase requisition and contract :
Then the flow should be as follow:
Thanks