We are using the production order and carrying the settlement of the production orders (posting to the FI after TECO). I would like to know in which table the following information is available.

Production order Number -

Date of Variance Posted -

Document Number Number -

Amount of the Variance

Kindly revert

Regards

Anilkumar

Accepted Solutions (0)

Answers (1)

Answers (1)

Former Member
0 Kudos

Hi,

table COEP, the object number is the order number 12 digits long, starting with OR.

To get variance settlement data, select COEP-VRGNG = KOAV (Settlement of variance data).

Best regards, Christian

Edited by: Christian Ortner on Mar 29, 2010 1:25 PM

b_amarendra
Explorer
0 Kudos

Hi,

In coep table settled cost is not there can we get batch wise settled cost in any tables.