hi,

what should i do if i want to set a contract validity check meaning that a PO cannot be created using a price from contract that validity end already expired.

Accepted Solutions (0)

Answers (1)

Answers (1)

Former Member
0 Kudos

Hi

You need to make the belwo messages as error in the below config

Application area - 06 - Message number - 041 - Validity period of contract expired on &

Application area -06 - Message number-042 -Target value of contract & exceeded by & &

Config path

Spro>MM>purchasing->Environment>Define attributes of system messages