cancel
Showing results for 
Search instead for 
Did you mean: 

Mandatory for price field

Former Member
0 Kudos

Hello,

How to make Gross price field as mandatory in CJ20N for service activity in network?

Prasad

Accepted Solutions (0)

Answers (2)

Answers (2)

former_member203108
Active Contributor
0 Kudos

But Thambi, the price field in service activity screen will be in non-editable....Why do you want to make that as mandatory field?

nitin_patoliya
Active Contributor
0 Kudos

You need to use exit CNEX0009 Material components in network.

With Regards

Nitin P.

virendra_pal
Active Contributor
0 Kudos

Exit is not required - that is for component - the question is for activity detail which can be configured

Transaction OPUC should suffice

nitin_patoliya
Active Contributor
0 Kudos

Tambi / Virendra,

Regret for inconvience, I have taken question on different front.

With Regards

Nitin P.

Former Member
0 Kudos

This message was moderated.

former_member203108
Active Contributor
0 Kudos

Dear we dont have field control for that screen in PS..may be you can check in MM configuration or consult your MM consultant. You will get the same screen even if you create Service PR...

virendra_pal
Active Contributor
0 Kudos

after changing config in OPUC i.e. changing price to mandatory for control key influence did you create a new network activity and check or did you check the old one?

Former Member
0 Kudos

This message was moderated.

former_member203108
Active Contributor
0 Kudos

Thambi, OPUC is available for network and network activity field selection....but what you are looking is not available in PS....as I said before it may be available in MM....

Former Member
0 Kudos

This message was moderated.

former_member203108
Active Contributor
0 Kudos

I have seen a field control for Service PR setting....try to set it from there and check...I am away from SAP system..the path could be MM>External service management>Scree or Field control......check that... and let us know whether it worked or not.

Former Member
0 Kudos

Ahmed,

Yeah....here i tried for CN21 ie create network.....inside i set gross field as mandatory.

Still system is allowing to save service activity without price.

Where i'm doing wrong?

Thanks

Thambi

former_member203108
Active Contributor
0 Kudos

Thambi, I cannot access system now and so couldnt cross check from my side....why dont you try creating new project and service activity and then check it....

Former Member
0 Kudos

Hi,

As told by Ahmed goto MM.

Follow the below path;

MM->External Services management -> Define Screen Layout.

Double click on Field Selection ML81--> Then Double click on Price and Value fields. Here you make Gross price as required entry.

Regards,

Kabir

Former Member
0 Kudos

Virendar, Ahmad, Kabir & All,

Thanks for your replies.

I tried that MM path.....for CN21 then for ML81

After doing this setting i created new WBS/ Network/ Activity(service)

But still it's not mandatory....

Kindly help me to solve this problem

Thanks

Thambi

Former Member
0 Kudos

Hello,

Kindly help me to find a solution for Price field as mandatory in Activity(services)

Thambi

Former Member
0 Kudos

This message was moderated.

Former Member
0 Kudos

This message was moderated.

former_member203108
Active Contributor
0 Kudos

Thambi, I tried my suggestion using field control for CN21 in MM path, even I dont get the price field as mandatory field, but instead of that I get an information message saying customizing is incorrectly maintained...I think it would be good if you consult with the MM person regarding how to maintain that settings correctly.

virendra_pal
Active Contributor
0 Kudos

you can do screen modification

SE51 program SAPLMLSP screen 400

double click on field ESLL-TBTWR and then go to program tab and change input to required

Former Member
0 Kudos

This message was moderated.

Former Member
0 Kudos

Thambi,

why don't you try with screen variant trnx SHD0?

Regards,

Praveen

Former Member
0 Kudos

Thambi,

I just tried screen variant through SHD0 transaction , I was successful in achieving this.

I have done it for CN21, CN22 and CJ20N as well. Its working fine. You have to create screen variant for 2 transactions Create network and Change network for CJ20N.

Regards,

Praveen

Edited by: b praveen savan on Mar 29, 2010 3:27 PM

virendra_pal
Active Contributor
0 Kudos

there is no implication as the modification is for the specific screen only

virendra_pal
Active Contributor
0 Kudos

you forgot CJ2B etc !

Former Member
0 Kudos

Thanks Virender.....as per your reply i'm going to do this.

Thambi