MRP run Creates PR even Open PO item is there

JavedA
Explorer
0 Kudos

I have a situation where MRP run is generating PRs for few materials although we have open PO with quantity more than the requirement for that particular material.

I have a material number setup as a HAWA

  • MRP Type : PD ; Lot Sizing Procedure: EX; Safety Stock: 5
  • I have open PO line with QTY scheduled to receive in the future
  • The PO creation date is 26-Nov-2018 and Delivery Date is 25-Dec-2018
  • Current inventory balance is zero
  • I am executing MRP (MD03 – Run MRP Single-Item, Single-Level)
  • MRP is proposing new PR with quantity 5 (equal to safety stock)

Accepted Solutions (0)

Answers (2)

Answers (2)

JavedA
Explorer
0 Kudos

Hi,

Thanks for response.

Configuration: Rescheduling Horizon: 100

The PO creation date is 26-Nov-2018 and Delivery Date is 25-Dec-2018

MRP Run Date: 20-DEc-2018

Regards

Javed

rafael_zaragatzky
Active Contributor
0 Kudos

Hi Javed,

Have you checked your planning horizon? MRP "doesn't see" any planned receipts beyond this horizon.

BR

Raf