Hi,
I need your opinion to resolve below issue.
1) We are running manually BBPGETVD to replicate newly created vendor to SRM and
2) BBP_VENDOR_UPDATE_DATA_JOB scheduled to update the R/3 vendor changes to SRM
Due to some issue we have cancelled this job and scheduled "BBP_VENDOR_SYNC" for updating the vendor changes to SRM
Now I came to know that "BBP_VENDOR_SYNC" is not only updating R/3 vendor changes to SRM but it is also replicating newly created vendor in to SRM (Which we don't want)
We donu2019t want to to replicate all newly created vendors to replicate in to SRM
We will replicate newly created (required vendor) by BBPGETVD
So the requirement is
How to restrict replicating of newly created vendor in "BBP_VENDOR_SYNC"
Thanks,
Jai